Upcoming Street and Sidewalk Projects

UPCOMING PROJECTS
CLA – East Street Recon, PID 94806 – This project consists of reconstructing East Street, from High Street to Grand Avenue. ODOT will be funding 80%, with the City funding the remaining 20%.
S. Limestone Sidewalk, Curb & Gutter – Sidewalk, Curb & Gutter repair will be required of the property owners on South Limestone Street from Miller Road to Leffel Lane. This project will be going out for rebid in the next week or so.
CLA – Trail Maintenance, PID 99562 – This project consists of trail maintenance items such as: signs, pavement markings, pavement repair and fence repair. Monies can only be spent on trails that are on City property or in dedicated right-of-way. ODOT will be funding 80%, with the City funding the remaining 20%.

Street Report 5/1/17

Villa Road:

Construction on the widening of Villa Road from Red Coach to Derr Road continues. Traffic will be maintained westbound from Derr Road to Red Coach Drive and a detour will be placed for eastbound traffic from Urbana Road to Derr Road. Eastbound local traffic only will be maintained from Urbana Road to Red Coach Drive The detour will be SR 72 (Urbana Road) to eastbound on Home Road to northbound on Derr Road.

Anticipated Completion Date: October 26, 2017

Street Report 4/3/17

Villa Road:

Construction on the widening of Villa Road from Red Coach to Derr Road has begun. Traffic will be maintained westbound from Derr Road to Red Coach Drive and a detour will be placed for eastbound traffic from Urbana Road to Derr Road. Eastbound local traffic only will be maintained from Urbana Road to Red Coach Drive The detour will be SR 72 (Urbana Road) to eastbound on Home Road to northbound on Derr Road.

Anticipated Completion Date: October 26, 2017

Columbia Gas Work Locations:

Cedar, Race, Light & Liberty Streets – (Fishel will be working in these neighborhoods performing restoration on the road and removing old gas mains out of service.)

Street Report

Belmont Avenue: South Belmont Avenue, between Kenilworth and Charles, will be closed during working hours March 28-30, 2017. The work will not begin until after lunch on March 28, 2017. This is necessary so that trees can be removed. Anticipate Completion Date: March...

Future Street Projects

CLA – Villa Road, PID 89421 This project consists of adding a center turn lane and multi-user trail between Derr Road and Red Coach Drive. Also, a new traffic signal will be installed at Red Coach Drive and Villa Road. In addition, the pavement from Red Coach Drive to...
Little Miami Trail Extension

Little Miami Trail Extension

Public Meeting A public meeting will be held for the Little Miami Trail Extension on October 14, 2010 from 5:30 pm to 7:30 pm at Perrin Woods Elementary School, located at 431 W. John Street, Springfield, Ohio. Project Description The proposed project will upgrade a...