Construction Project Updates

Erie Interceptor Express Sewer

Work continues on the Erie Express Sewer Project. Work is now focused on the W. First Street / Skinner Lane area. Crews are working on W. First Street placing bores under the roadway. At the new lift station site, crews have begun building the above ground portion of the new pump station facility. Also, restoration work continues throughout the project. No roads are closed at this time. Please be aware of construction traffic entering and exiting different areas along the construction route. This work is being completed by Kokosing Industrial and the anticipated completion date is November 2018.

CLA – Bechtle Signals, PID 98859

The CLA – Bechtle Signals project consists of replacing signal controllers and equipment, adding video cameras and spread spectrum radios and a signal being reconstructed. This  project is located on Bechtle Avenue at the intersection of SR41 (Troy Road). This project was awarded to Bansal Construction on June 6, 2017 and the anticipated completion date is April 30, 2018.

Funded by ODOT.

Miscellaneous Sanitary Sewer Lining, Phase I

This project consists of installing various sizes of sanitary sewer lining at the following locations – E. Pleasant Street (between Limestone St. and Vine St.) – includes 8 manhole castings removed and replaced, 13 manholes lined and 31 laterals and Vine Street (439 Vine St. to Monroe St.) – 21 laterals and 12 manholes lined. It will also include meandering through Easements (Gallagher Street, Vine Street, E. Pleasant Street and Linden Avenue) – includes 8 manhole castings removed and replaced, 17 manholes lined and 8 laterals. The project was awarded to Layne Inliner, LLC. Anticipated completion date of June 1, 2018.

2017 Miscellaneous Water Replacement

This project consists of waterline replacement on Lawnview Avenue, Drexel Avenue and Euclid Avenue. Crews are currently working on Lawnview Avenue. Please be aware of construction traffic entering and exiting the project area. Traffic will be maintained to local residents with intermittent delays. The contractor for this project is  J & J Schlaegel, Inc. for an awarded contract amount of $674,074.50 and an anticipated completion date of April 27, 2018.

Funded by the City.

2017 Miscellaneous Sanitary Sewer Lining

This project consists of rehabilitation of approximately 400 vertical feet of manhole utilizing spray applied monolithic liner and rehabilitation of approximately 9,000 linear feet of existing sanitary sewer by cured in place plastic pipe (CIPP) process. The contractor for this project is Inland Waters Pollution Control for an awarded contract amount of $476,664.85. Anticipated completion date is July 31, 2018.

Funded by the City.

UPCOMING CONSTRUCTION PROJECTS

CLA – Trail Maintenance, PID 99562 – REBID – This project consists of pavement repair and resurfacing various segments of the multi-use trail system maintained by National Trail Parks and Recreation. Bid opening date is scheduled for February 2, 2018.

CLA – US 40-16.82, PID 103791 – This project consists of replacing the spanwire traffic signal supports with mast arms to add 5-section signal heads and add backplates to all traffic signal heads at the intersection of Bird Road and Route 40. Bid opening date is scheduled for February 9, 2018.

2017 Miscellaneous Sewer Replacement – This project consists of miscellaneous sewer replacement on Mound Street, Jasper Street and Merritt Street. Bid opening scheduled for February 16, 2018.

Buck Creek Trail Realignment Project – This project consists of realigning a portion of the Buck Creek Trail in the City. Bid opening scheduled for February 16, 2018.

 