The Engineering Department provides planning services that preserve the health, safety, and welfare of the community through the application of plans, codes, and ordinances for the City’s best uses of resources and development.

Road Closure – Extended due to weather

Harding Road 

Construction has begun on Harding Road, between Fountain and Limestone Street. Columbia Gas is working on their service lowerings and will be working in the same zone as the City’s contractor. For the safety of the motoring public and the construction workers, Harding Road, between Fountain and Limestone will be closed from 7am to 6pm each day through Wednesday, February 27, 2019.

 

Bid Tabulations / Awards

Award Information

 

Bid Tabulations

Specifications

Curb, Gutter & Sidewalk Specifications

Click here to view specifications.

 

Construction Specifications and Standard Drawings

Click here to download complete book.

 

Construction Specifications

 

Standard Drawings

 

Project Award Information
Street Report

 

Street Report for the Week of February 25, 2019

Street Report 2.25.19

Harding Road:

Construction is underway on Harding Road, between Fountain and Limestone Street. Columbia Gas has begun the service lowerings and will be working in the same zone as the City’s contractor until Wednesday, February 27, 2019. For the safety of the motoring public and the construction workers, Harding Road, between Fountain and Limestone will be closed from 7am to 6pm each day. An update will be posted the end of the week for future traffic maintenance during this construction project.  

Anticipated completion date is July 26, 2019

 

Bechtle Avenue (over Snyder Park Road):

Traffic will be restricted to one lane in each direction on Bechtle Avenue from Keifer Avenue to Perry Street. A detour will be posted for closure of Snyder Park Road under Bechtle Bridge.

Anticipated Completion Date: August 30, 2019

Additional Road Closures (county projects)     Clark County Road Closures

 

Permit Applications

Permit Applications

Please Note: Public Right of Way Application can be submitted the following ways:

  1. Download, print and complete the application. Turn in the completed application, with all required documentation , in person, Engineering Department, 2nd Floor, City Hall, 76 E. High Street, Springfield, OH 45502.
  2. Download, print and complete the application. Return to the Engineering Department by email to mmccuistion@springfieldohio.gov or by mail to the City of Springfield, Engineering Department, 76 E. High Street, Springfield, OH 45502.
  3. Download ‘fillable’ PDF form to your desktop and complete. Then, using the ‘Submit’ button, return electronically.

After the application has been received, you will be notified of revisions or amount of payment.

Helpful Resources
Projects Under Construction

 

CLA – Middle Urbana Rehab, PID 94768

This project involves the widening, partial full depth reclamation and overlay of Middle Urbana Road from an existing two lane highway with shared two way left turn lane. Work includes pavement widening, minor drainage improvements, sanitary and water upgrades and ditch grading along Middle Urbana Road, between Villa Road and S.R. 334. This project was awarded to J & J Schlaegel, Inc. in the amount of $1,394,613.15.

Roadway is open to two way traffic. Unfortunately, the project will not be completed this year. The contractor shall be working throughout the winter, as weather will allow and the final course of asphalt will be placed in the spring.

Please be aware that work zones shall be in place at various locations along the project as the contractor works on different items.

Funded by ODOT, OPWC, City Water & City Sewer.

 

CLA – US 40-16.82, PID 103791  – Rebid 

This project consists of replacing the spanwire traffic signal supports with mast arms to add 5-section signal heads and add backplates to all traffic signal heads at the intersection of Bird Road and Route 40.  U.S. Utility Contractor is the contractor on the project. Cost of the project is $233,818.34. The contractor is currently scheduled to set the new mast arms in January 2019. The anticipated completion date is sometime in February of 2019.

Funded by ODOT.

 

2018 Miscellaneous Sanitary Sewer Lining 

This project consists of:

  • Rehabilitation of approximately 375 vertical feet of manhole utilizing spray applied monolithic liner.
  • Cleaning and Rehabilitation of approximately 5,512 linear feet of existing sanitary sewer by cured in place plastic pipe (CIPP)

The locations where the lining will be taking place are: S Jackson St – W State St to Innisfallen Ave; S Clairmont Ave – Sheridan Ave to Van Buren Ave; S Clairmont Ave – Van Buren Ave to Lexington Ave; Lexington Ave – S Douglas Ave to S Clairmont Ave; Lexington Ave – Raffensperger Ave to S Clairmont Ave; Lexington Ave – Buxton Ave to Raffensperger Ave; Lexington Ave – Burnett Rd to Willow Dr; Lexington Ave – S Belmont Ave to S Douglas Ave; and N Market St – S Center St to S Fountain Ave. Anticipated completion date is scheduled for November 30, 2018. The contractor on this job is Insituform Technologies, LLC. with an award amount of $343,494.00.

Funding provided by City Sewer funds.

CLA – Bechtle – 0.57, PID 99563

This project consists of bridge rehabilitation on Bechtle Avenue over Snyder Park Road and Lagoons by replacing the superstructure with minimal approach work. Bid was awarded to Eagle Bridge Company with a bid amount of $1,409,565.61. Two-way traffic shall be maintained with on lane of travel in each direction. Please be aware of traffic lane shifts and exercise caution as construction traffic may be entering and exiting the work zone. Scheduled completion date is 8/30/18.

Funding provided by ODOT and OPWC.

Share This