The Engineering Department provides planning services that preserve the health, safety, and welfare of the community through the application of plans, codes, and ordinances for the City’s best uses of resources and development.

   ROAD CLOSURE

MIDDLE URBANA ROAD

The contractor will begin removing trees for the Middle Urbana Rehab project along the west side of Middle Urbana Road, between Villa Road and SR 334 on Monday, February 12, 2018. Traffic will be maintained by use of a mobile traffic signal during working hours so delays could occur throughout the day. This work is expected to take approximately 2 weeks.

Bid Tabulations
Specifications

Curb, Gutter & Sidewalk Specifications

Click here to view specifications.

 

Construction Specifications and Standard Drawings

Click here to download complete book.  

 

Construction Specifications

 

Standard Drawings

   

Project Award Information
Street Report

For the Week of February 5, 2018

Street Report 2.5.18

Middle Urbana Road:

Contractor will begin removing trees for the Middle Urbana Road Rehab project along the west side of Middle Urbana Road, between Villa Road and SR 334 on Monday, February 12. Traffic will be maintained by use of a mobile traffic signal during working hours so delays could occur throughout the day.

Anticipated Completion Date: February 26, 2018

 

Columbia Gas Work Locations:

Main Street

Broadway Street

Anticipated Completion Date: February 9, 2018

 

 

 

Additional Road Closures (county projects)     Clark County Road Closures

 

Permit Applications

Permit Applications

Please Note: Public Right of Way Application can be submitted the following ways:

  1. Download, print and complete the application. Turn in the completed application, with all required documentation , in person, Engineering Department, 2nd Floor, City Hall, 76 E. High Street, Springfield, OH 45502.
  2. Download, print and complete the application. Return to the Engineering Department by email to mmcuistion@springfieldohio.gov or by mail to the City of Springfield, Engineering Department, 76 E. High Street, Springfield, OH 45502.
  3. Download ‘fillable’ PDF form to your desktop and complete. Then, using the ‘Submit’ button, return electronically.

After the application has been received, you will be notified of revisions or amount of payment.

Helpful Resources
Projects Under Construction

Erie Interceptor Express Sewer

   

Work continues on the Erie Express Sewer Project. Work is now focused on the W. First Street / Skinner Lane area. Crews are working on W. First Street placing bores under the roadway. At the new lift station site, crews have begun building the above ground portion of the new pump station facility. Also, restoration work continues throughout the project. No roads are closed at this time. Please be aware of construction traffic entering and exiting different areas along the construction route. This work is being completed by Kokosing Industrial and the anticipated completion date is November 2018.

CLA – Bechtle Signals, PID 98859

The CLA – Bechtle Signals project consists of replacing signal controllers and equipment, adding video cameras and spread spectrum radios and a signal being reconstructed. This  project is located on Bechtle Avenue at the intersection of SR41 (Troy Road). This project was awarded to Bansal Construction on June 6, 2017 and the anticipated completion date is April 30, 2018.

Funded by ODOT.

Miscellaneous Sanitary Sewer Lining, Phase I

This project consists of installing various sizes of sanitary sewer lining at the following locations – E. Pleasant Street (between Limestone St. and Vine St.) – includes 8 manhole castings removed and replaced, 13 manholes lined and 31 laterals and Vine Street (439 Vine St. to Monroe St.) – 21 laterals and 12 manholes lined. It will also include meandering through Easements (Gallagher Street, Vine Street, E. Pleasant Street and Linden Avenue) – includes 8 manhole castings removed and replaced, 17 manholes lined and 8 laterals. The project was awarded to Layne Inliner, LLC. Anticipated completion date of June 1, 2018.

2017 Miscellaneous Water Replacement

This project consists of waterline replacement on Lawnview Avenue, Drexel Avenue and Euclid Avenue. Crews are currently working on Lawnview Avenue. Please be aware of construction traffic entering and exiting the project area. Traffic will be maintained to local residents with intermittent delays. The contractor for this project is  J & J Schlaegel, Inc. for an awarded contract amount of $674,074.50 and an anticipated completion date of April 27, 2018.

Funded by the City.

2017 Miscellaneous Sanitary Sewer Lining

This project consists of rehabilitation of approximately 400 vertical feet of manhole utilizing spray applied monolithic liner and rehabilitation of approximately 9,000 linear feet of existing sanitary sewer by cured in place plastic pipe (CIPP) process. The contractor for this project is Inland Waters Pollution Control for an awarded contract amount of $476,664.85. Anticipated completion date is July 31, 2018.

Funded by the City.

UPCOMING CONSTRUCTION PROJECTS

CLA – Trail Maintenance, PID 99562 – REBID – This project consists of pavement repair and resurfacing various segments of the multi-use trail system maintained by National Trail Parks and Recreation. Bid opening date is scheduled for February 2, 2018.

CLA – US 40-16.82, PID 103791 – This project consists of replacing the spanwire traffic signal supports with mast arms to add 5-section signal heads and add backplates to all traffic signal heads at the intersection of Bird Road and Route 40. Bid opening date is scheduled for February 9, 2018.

2017 Miscellaneous Sewer Replacement – This project consists of miscellaneous sewer replacement on Mound Street, Jasper Street and Merritt Street. Bid opening scheduled for February 16, 2018.

Buck Creek Trail Realignment Project – This project consists of realigning a portion of the Buck Creek Trail in the City. Bid opening scheduled for February 16, 2018.

 

 

Part 9 - Streets, Utilities, and Public Services Code
Share This